🏭 Time to obtain an electrical connection
Average wait, in days, experienced to obtain electrical connection from the day this establishment applied for it to the day it received the service.
1
🇵🇱Poland
282.5 days
2
🇳🇱Netherlands
183.5 days
3
🇳🇴Norway
177.7 days
4
🇸🇷Suriname
114.9 days
5
🇻🇨Saint Vincent and the Grenadines
108.1 days
6
🇧🇪Belgium
106.6 days
7
🇳🇪Niger
102.5 days
8
🇪🇬Egypt
88.8 days
9
🇨🇿Czechia
79.4 days
10
🇨🇱Chile
74.6 days
11
🇫🇷France
68.5 days
12
🇫🇯Fiji
59.8 days
13
🇩🇪Germany
59.1 days
14
🇩🇰Denmark
55.7 days
15
🇰🇲Comoros
50.9 days
16
🇱🇰Sri Lanka
47.0 days
17
🇪🇹Ethiopia
44.2 days
18
🇲🇳Mongolia
42.8 days
19
🇧🇮Burundi
38.1 days
20
🇦🇫Afghanistan
37.0 days
21
🇱🇹Lithuania
35.2 days
22
🇬🇹Guatemala
34.7 days
23
🇧🇿Belize
33.9 days
24
🇲🇼Malawi
31.3 days
25
🇺🇬Uganda
29.3 days
26
🇧🇷Brazil
28.0 days
27
🇵🇦Panama
27.6 days
28
🇹🇹Trinidad and Tobago
27.1 days
29
🇨🇭Switzerland
25.8 days
30
🇰🇪Kenya
25.7 days
31
🇳🇬Nigeria
24.7 days
32
🇯🇵Japan
24.5 days
33
🇱🇷Liberia
24.5 days
34
🇲🇻Maldives
22.6 days
35
🇲🇿Mozambique
22.2 days
36
🇫🇮Finland
22.1 days
37
🇧🇴Bolivia
21.8 days
38
🇦🇬Antigua and Barbuda
19.9 days
39
🇿🇼Zimbabwe
19.6 days
40
🇦🇺Australia
19.4 days
41
🇦🇱Albania
19.2 days
42
🇩🇴Dominican Republic
18.5 days
43
🇩🇯Djibouti
18.1 days
44
🇸🇧Solomon Islands
17.6 days
45
🇹🇭Thailand
17.2 days
46
🇶🇦Qatar
16.8 days
47
🇦🇹Austria
16.6 days
48
🇬🇼Guinea-Bissau
15.9 days
49
🇱🇨Saint Lucia
15.3 days
50
🇰🇮Kiribati
14.4 days
Highlights
As of 2025, Poland ranks first with 282.5 days, followed by Netherlands (183.5 days) and Norway (177.7 days).
Poland is 1.5 times higher than Netherlands, the runner-up.
Across 61 countries and territories, values run from 282.5 days (Poland) to 3.0 days (Kuwait), with a median of 24.7 days.
By region, the top 10 is made up of 5 from Europe, 3 from the Americas and 2 from Africa.
Source: World Bank Open Data — Time to obtain an electrical connection (days), 2025. Unit: days.
Source: World Bank Open Data — Time to obtain an electrical connection (days) · CC BY 4.0 · fetched Oct 16, 2026